Week 3 Experience

This week i spend my time in learning Docker and understanding how we can Dockerize the complete project in future. Dockerizing the complete project will help in easy deployment. For easy monitoring, I created a new repository in my github account.

Tickets I worked on:

we still working on the FM-395 and FM2–403. Hopefully we will get it merged next week. For tracking all the code update for docker, i have created a new repository in my github account:

openmrs-keycloak-dockerized-setup: https://github.com/theanandankit/openmrs-keycloak-dockerized-setup

We commited our initial code to github and working on docker-compose file.

Week 4 Plan:

Our main task will be to successfully dockerize the complete SMART-on-FHIR project and start working on our SMART app.

--

--